Royal Oak Landslip Repairs - Official Report
History
Just south
of Greet Tunnel on the Cotswold side of the track, the line is in a cutting and
the side has been subject to slipping for many years.
There is evidence of remedial works being done in BR days but with limited effect.
There was a manhole at the top of the cutting to collect the water from the
fields but by 2011 it looked like this:
By 2015, it
had deteriorated to this:
By September
2017, sufficient funds were available to make a partial repair to the damage.
This involved constructing a new manhole at the top of the slope connected to
the drains from the fields together with a new outlet pipe taking the water
down to the track drains. In this picture, the new manhole can be seen above
the excavator arm with the new outlet pipe being laid under the arm:
This shows
how close the slip was to the railway boundary together with the new manhole
and drains indicated by the stone:
Because of
the limited funds, a proper reconstruction of the slope was not possible so the
existing soil was reformed to provide a smooth slope:
Unfortunately
the winter of 2017/2018 provided unusually wet especially over the Christmas
period and the reformed slope was undermined by water flow causing a new slip.
As the ground slipped down, it took the outlet pipe with it so that the water
from the manhole was now flowing on to the slope making things worse. The
ground was so soft and precarious, it would not have been safe to attempt an
emergency fix at this time:
Conditions
worsened until the new manhole was completely exposed:
It took the
months of dry weather to dry out the ground and by this time, further funds
were available. A consultant, David Symonds
Associates, was engaged to prepare a design and drawings and then three firms
were invited to tender to complete the repair works. After evaluating the
tenders, Walsh Construction was awarded the contract. As a bonus for the
railway, they had just had a project delayed so were able to start on site just
a week later on 17th September 2018 to take advantage of the
continuing dry weather. The railway had already negotiated access across the
fields with the neighbouring land owners and Walsh starting constructing an
access road immediately:
In order to
protect the site in case of further rain, the first task was to install new
drainage in one of the fields so that any water was collected and sent to the
manhole before it could soak the slipped area. A series of pipes surrounded in
stone and membrane were laid in a herring bone pattern and then the topsoil was
replaced:
Whilst the
small excavator carried out this work, its larger companion finished off the
access road and then started excavating the soil from the slipping area and
putting it into a stockpile. After discussions with our consultant, this
material was declared unsuitable for reuse and was removed from site:
The soil at
the toe of the embankment was excavated down until hard clay was encountered
below the slipped material. During this work, a clear slip zone could be seen
in the face of the excavation between the lower hard clay and the softer upper
clay sloping back up the embankment.
Water was percolating along this zone lubricating the surfaces and
therefore aiding gravity to move the upper material down. This zone was in a
bowl or valley shape and the excavation was taken beyond this on each side to
ensure that it was removed. The excavation was brought up in a series of
benches with the excavated material being passed from one excavator to the
other and thence to the stockpile:
The shape of
the slip zone determined the size of each bench and once most of the failed
material was removed, work started on rebuilding the slope. A geotextile
membrane was spread over the hard clay to keep the new fill separate and the
stone was placed on top in layers and compacted with either a roller or a large
‘Wacker’ plate:
Initially
only a thin layer of stone was placed to hold the membrane in place and protect
the exposed good clay in case of rain whilst excavation continued at higher
levels:
Then more
stone was placed and graded to the required slope:
As the level
of the stone fill rose, the new pipe to connect the top manhole down to the
track drains was installed:
As the
benches rose, the working area got smaller and a Wacker plate was used instead
of a roller:
At this
stage, the topsoil that had been saved was spread over the surface of the
stone:
In order to
hold the topsoil in place, a membrane was laid on top and pegged down:
As the stone
got close to the final level, the drain along the crest of the embankment was
reinstated surrounded in free draining stone and a membrane:
Here the
stone fill is being placed before excavating for the crest drain visible in the
background:
After the
drainage was completed, the slope was topsoiled and the protective membrane
laid before the entire area was hydro seeded:
New fencing
was then erected, the temporary access road removed and the field reinstated:
A view of the
completed works:
As a bonus,
the material used in the temporary access road was taken around to Working Lane
to improve our access up towards the tunnel:
Report and photographs by Alastair Watson.