BRIDGE 12 - STANWAY VIADUCT – KING-POST GROUND
STABILISATION PROJECT
As with a few of our bridges the viaduct has a problem
with ground erosion where the brick wing walls end and the embankments start. This
slowly causes the track bed to become undermined.
All 4 corners of the viaduct
are affected to some extent, those at the north end being the worst.
Current ballast restraint, north end of Stanway viaduct. |
Some years
ago a retention scheme using redundant concrete sleepers was installed, but the
ground movement has slowly continued, allowing the sleepers to start leaning.
At the north end on the upside the ground of the sloping embankment
is now almost 1M below the track bed level.
Following a massive vegetation clearance by our
clearance team, a detailed topographical survey was carried out by Surveyors,
Horner’s from Evesham, to establish the existing ground profile.
Then, to
identify what the soil was like, a ground investigation was carried out by
G.I.P. of Wolverhampton using a tripod drilling rig, and soil tests
were done on the samples taken.
With this information available, a scheme has been
designed by consultant J. Symonds to provide a more permanent
solution. The contractors - Walsh’s of Worcester - started work on Wed. 13th
Feb.
Trench |
The first task was to excavate a trench deep enough for the new “walls”
and to make room for drilling holes for the king-posts to be installed. Next a 360 excavator with an augering tool attached drilled holes app
450mm diam. down app. 3M into the ground.
Channel section attached to brickwork. |
Galvanised steel columns and brackets. |
Then 152 x 152 steel column
sections, with a galvanised finish, were lowered into each hole and were
concreted into place.
Because the ground is clay dumped from the cutting
excavations it is not very well consolidated and so the tops of the king-posts
will be tied together with steel bars below the track bed, using the brackets
which are just visible. Where the viaduct walls end a 150 x 90 R.S. channel
section is bolted to the brickwork.
Once the concrete has hardened sufficiently concrete
sleepers, which are no longer suitable for track laying, are lowered into the steel
sections.
The next task will be to excavate a narrow trench
beneath the track bed to take the 25mm diam tie bars.
Once the tie bars are in place the space between the
new sleeper wall and the edge of the track bed will be filled with ballast to
stabilise the edges, which were starting to be undermined.
BR’s 24 (GREET TUNNEL), 43 (A435 – EVESHAM ROAD
BRIDGE) & BR. 44 (HUNTING BUTTS TUNNEL) – DETAILED EXAMINATIONS. Mon. 18th
to Thursday 21st Feb. incl.
As part of our continuing bridge examination
programme, these 3 structures were due for their Detailed Examination, which we
aim to do at no more than 6 year intervals. This matches the time scale used
by Network Rail. These are fitted around the Annual Visual Inspections
currently being done by our engineer – Alastair Watson.
As with all our structures vegetation is a constant
nuisance and a very large clearance job was organised by Mike Peers using two
contractors. That work extended to the land at the south end of Hunting Butts tunnel and
right down to Br. 45 (Swindon Lane), to enable a detailed examination of the
south end of Hunting Butts tunnel & Br. 45 Swindon Lane to be done later in the
year.
Br. 24 (Greet tunnel) – Due to the size of these structures (app
7.5M to the crown of the brick arches) it is necessary to use a MEWP (Mobile
Elevating Working Platform – railway name & abbreviation for a cherry
picker).
Road/Rail MEWP |
Unfortunately there is no road access to the tunnel and so a much more
expensive Road/Rail MEWP has to be used. This was transferred from road to rail
in Winchcombe yard, where it travelled up to the Greet tunnel. The
examination work took 2 days (more photos to follow).
Br. 43 (A435 Evesham Road Bridge) – This is a 3-arch brick structure carrying the
busy A435 road to Evesham. We had a choice of a Road/Rail MEWP, or an underbridge unit. A Road/Rail MEWP has some restrictions in trying to get into
the two side arches and so we decided to use an underbridge unit instead.
This
machine would be parked on top of the bridge and thread its arms wherever it
could. The road had to have a half closure and we had to provide traffic
management. Glos. C.C. restricted us to between 9.00 a.m. and 4.00 p.m. This took just one day and more photos will follow.
Br. 44 (Hunting Butts tunnel) – This tunnel has always been packed with wagons (mostly awaiting removal from the railway), since the tracks were first
laid into it nearly 20 years ago.
Privately owned goods wagons drawn out of the tunnel. |
All of these had to be dragged out and
parked in P. 2 at CRC, with some from the down side shunted onto the
up side, just outside the tunnel.
Inspection of north portal of Hunting Butts tunnel. |
The final photograph shows the MEWP with engineers on
board, inspecting the north portal. The work took just one day.
23.2.2019 - JOHN BALDERSTONE
Photos courtesy of Alastair Watson, John Balderstone
& Jonathan Symonds.