Sunday, 9 September 2018

Update on Broadway




BRIDGE 1 – COLLISION PROTECTION BEAM – WEEK 1 OF INSTALLATION

As mentioned last week, work on site on the north abutment started on Monday 3rd Sept. In the last blog we reported that the two half length steel channel beams had arrived and 4 No. Mabey temporary support columns had been erected and bolted to the walls.

 




By Wednesday each half beam has been raised and manoeuvred into position and roughly to the correct level, using chain blocks attached to the bridge beams. 











Lifting the two half beams.

 


 
Extension pieces of Mabey columns were then bolted to the outer faces, at the tops of the main columns, to prevent the channel beams toppling over as the huge end brackets make them top heavy and unstable. 














Then the whole channel was raised to the correct level and packed there.




 
The joint between the two half beams
These two halves were then bolted together at the centre.

To make room for the new CPB’s the wasp stripe panels have been temporarily removed and will be attached to the new CPB beams spanning the road later. In addition the electric cables and conduits providing power to light the headroom warning signs have also had to be relocated temporarily.
 
Drilling holes into the abutment.
With the abutment channel beam now in place, drilling the 40 No. 35mm diam holes, extending 650mm into the abutment brickwork, was started. These will eventually take the 30mm diam resin anchor bolts. By Friday afternoon, all 40 holes had been drilled to a depth of app. 400mm.
 
General view of site, with drilling in progress.
As is the case with many of our bridges both abutment walls lean towards each other. At Broadway the lean is app 200mm in the 4.4M height. We believe that the reason for this is that the construction of the embankments was started before the brickwork had hardened sufficiently and so the brickwork (between 900mm thick at the top and about 2.2M at the bottom!!) was slowly pushed over as the embankment level rose. This line was built in a rush (some viaduct arches also fell down!!!), and we think that this was the result. When we did the major repairs and renovations in 2014 we discovered that the steel beams overhung the padstones at both ends – we imagine that the steel fabricator (Edward Finch of Chepstow) was somewhat baffled when they came to install them!!

As a result of this lean and some unevenness in the brickwork generally, the channels will have to be set vertically and packed in place. Then cement grout will be fed into the gap behind to fill the gap, which will be app 12mm wide at the top and 35 to 40mm at the bottom.

Once the CPB work is done on this side, the contractors have to do a small amount of minor repairs (scratched paint and wasp stripe panel replacement) to damage done on 1st May 2018, for which insurers AXA will be paying.

Then the road closure arrangements will be switched over to the south half of the road and the similar work repeated on that abutment.




 8.9.2018 - John Balderstone and John Fancote

10 comments:

  1. Hi John & John, Thanks for the update; it's looking good. Reference the picture of Hyde Lane in the previous post, will the bridge abutments at Broadway be built up to the bottom of the channel beam to match?
    Also, how much lower will the protection beam be than the bottom of the bridge?
    Many thanks, Andrew.

    ReplyDelete
  2. Thanks for the update; much appreciated!

    Noel

    ReplyDelete
  3. Andrew,
    I am not sure why Hyde Lane was built with a step in the abutments, but ours are thick enough not to need anything like that. The underside of the CPB has to be set 20mm below the lowest point (in our case the heads of the rivets under the centre of the main girders).

    ReplyDelete
    Replies
    1. John,

      When you have completed the work on the north side of Broadway Rail Bridge, will you use a crane to maneuver the steel beams across the road, or will it be the same 'pulley arrangement' that you are currently using?

      Thanks for the ongoing updates.
      Mark.

      Delete
    2. Mark,
      The brackets on the South abutment will be handled the same way as those being fitted to the North abutment.
      The Protection Beams spanning the road will be lifted in using a small crane with a temporary full road closure.

      Delete
  4. GREAT report. Detailed and informative to all.

    I am really excited by this work, as it is pro-active in preventing potential FURTHER bridge strikes.

    Looking forward to further updates.

    ReplyDelete
  5. When the CPB's are fully installed I wonder who's lorry will have the dubious distinction of being their first 'victim'?

    ReplyDelete
    Replies
    1. Perhaps the railway should get Specsavers to sponsor a trophy for the first lorry driver to hit it !

      Delete
  6. I really like the simple and elegant way the beam was lifted into place using chain blocks - probably similar technology to when the bridge was originally built! Do the actual anti collision beams come filled with concrete or is that done on site?

    ReplyDelete
  7. There was really no choice for lifting due to it being under the bridge itself. It worked well but was hard physical work! The actual CPB cross beams will be filled with concrete in the factory, mainly because we need to keep the total road closure as short as possible, and this will take quite a long time. It does mean that they will have to lift 5.5T. instead of 1.4T.

    ReplyDelete