A new title for this blog, but just as much news. Actually, maybe even more, as it will now also feature other news from our civil engineering activities.
We carry on with:
We carry on with:
BRIDGE 09 – AQUEDUCT/ PEDESTRIAN FOOTBRIDGE – FIRST WEEK'S ACTIVITIES
The contractors came to site on Monday 28th
October to set up their welfare and stores and other H & S
requirements. A line possession was put
in place starting on Thursday 1st November and work done at track
level commenced. The first job was to remove the timbers forming the pedestrian
walkway. This exposed the horizontal leg of the steel angle to which the
timbers were attached.
As you can see (photos) this ½” thick steel has been dramatically eaten away all along.
Tremendous quantities of scale were also exposed, both on the top of the angle and also within the channel as well.
In places between 1.5 & 2m long sections of the top angle had completely gone. Just what supported the timber over those areas is a mystery. It’s a good job we closed it to pedestrians several months ago!!!
As you can see (photos) this ½” thick steel has been dramatically eaten away all along.
Tremendous quantities of scale were also exposed, both on the top of the angle and also within the channel as well.
In places between 1.5 & 2m long sections of the top angle had completely gone. Just what supported the timber over those areas is a mystery. It’s a good job we closed it to pedestrians several months ago!!!
The next job was to provide support to the inner ends
of the two outer spans to enable them to be cut away from the centre span, which
was supported on the two brick piers. The support to the outer spans was
provided by scaffolding which had jacks at the top to support the steel
channel.
The scaffolding was also there to provide stability to the slender brick piers during the dismantling work, and to provide access to cut the steel channel.
The scaffolding was also there to provide stability to the slender brick piers during the dismantling work, and to provide access to cut the steel channel.
Next the ends of the steel channel had to be freed from the concrete encasement at each end.
The channel could then be cut through to leave it in 3 separated sections, weighing between 3 and 4 tonnes each.
Then a mat of stone had to be prepared for the crane to sit on so that the outriggers would clear the rails.
Last Thursday the 60t capacity crane came to site and its first job was to lay down timber pads for the outriggers to sit on.
The tubular hand rails had been left until the last minute, to provide stability to the structure and were only cut through when the section was being supported by the crane.
With all outriggers deployed lifting was started, taking the Malvern side span out first.
Then the centre span...
....and finally the Cotswolds side span.
The 3 sections (11 to 12m long) were laid down
alongside the track and will be cut up and put in a skip, to go off site.
Work then commenced on the Cotswold side bank seat. First the stream (bone dry at the time!!) was blocked off and diverted down the embankment to our trackside drains.
Photo in which the stream blocking bags and black plastic diversion pipe can also be seen |
Photos courtesy of John Balderstone, John Fancote
& Richard Griffiths (Stepnell)
10.11.2018 - JOHN BALDERSTONE
Additional photographs from another angle:
Additional photographs from another angle:
All three sections of the aqueduct removed |
Detail of corrosion:
Directly through the side of the channel
Top flange and handrail bracket eaten away.
Cross section through the channel,showing varying thicknesses. The principal corrosion is in the lower half, where the water ran.
Section of channel showing corrosion of the flanges that supported the wooden walkway
Maker's plate:
E. Finch & Co Ltd.
Engineers
1904
Iron Founders
Chepstow
Cotswolds side pad on which the channel rested, temporary dam and pipe channeling the stream to the trackside drain. It was dry at the time of the photograph.
There was a significant leak here, as the stream took a shortcut down to the bottom right.
View of the pillars looking west |
View of the pillars looking east, and Malvern side pad. |
Malvern side pad and underground channel leading away. This pad was rebuilt by the railway in 2002. |
Thanks Jo, fascinating stuff.
ReplyDeleteThere is plenty more fascinating stuff to come, we have plenty of plans. There is a good feeling about the railway.
DeleteNow that the extension to Broadway is mostly done, and a number of vital repairs (e.g. the skew bridge, but also this) attended to, it will be fascinating to see where funded is directed to next!
DeleteNoel
Fantastic progress, hopefully the works will continue to go well. Keep up the good work.
ReplyDeleteAmazing coverage, thanks to all involved in putting it together!
ReplyDeleteNoel
Will the builder's plate be salvaged?
ReplyDeleteI asked and I think they will put it to one side. However, it is broken in half. That is usually the fate of any of the bridge builders plates, left outside. Rust builds up behind them, and they break. The one on the other side is in several pieces BTW.
DeleteTo make the replica 1903 ones for the Broadway canopy and footbridge we borrowed a clean one from a supporter, and his used to be inside the Broadway canopy and was therefore intact.
I have a spare replica 1903 one at home, which will go on the P2 canopy at Broadway.
Ok, thank you. I figured you had a plan!
Delete