Sunday, 10 March 2019

Work at Stanway viaduct



BRIDGE 12 - STANWAY VIADUCT – KING-POST GROUND STABILISATION PROJECT – work completed.





Following the completion of the new King-post sleeper walls, the old sleeper walls were removed.



























This left the north end more or less completed, as in these two pictures.











 Work then started on the south end.




















The south end proved to be a bit more problematical because of the gabion baskets on the upside, close to which were two signal cables. This did not leave much room to feed the 450mm diam auger between the two but it got done with slight disruption to the back of the gabion baskets. On the downside things were slightly easier.


Once the steel columns were concreted in the concrete sleepers were dropped in on both sides, then the tie bar installation was started. 


This involved trenching between the sleepers.



















The tie bars are to there to anchor the tops together, which enabled a shorter length for the steel posts to be used.  Without the tie bars the resistance to the outward movement of the track bed fill and ballast would be entirely provided by sidewards ground resistance against the concrete casings to the steel posts. 










To simplify the installation, the tie bars were in 3 pieces with couplings to fasten them together. 







 




One of the problems encountered in one section, was where cement grout had been mixed with the ballast to create a large concrete lump which had to be broken out to allow the trench to be dug.




After the tie bars had been tightened up the side trenches were filled to restore the ballast levels back to the original and the ground outside the new walls could be regraded.



At the north end, the difference between the track level and the original ground was greater, as can be seen from the step down from inside to out. There was limited scope for levelling there.

The final task was to try to locate the Inspection chambers for the viaduct drainage. Unfortunately, by installing the track down the centre of the viaduct, they were all buried preventing any maintenance. 


With no real details of where they were we dug down to find one.






Finally, the above two photographs show the completed stabilisation works.

Photos courtesy of Alastair Watson, John Balderstone & Peter Muir.***

The pictures in this blogpost have been removed on request.


8.3.2019 - JOHN BALDERSTONE

9 comments:

  1. great work on the viaduct , most impressive and good luck at Stanton , john M.

    ReplyDelete
  2. I assume, that with regard to the Tiebars, consideration has been given to the depth that tamper tines go down below sleeper bottom.

    I think that another version of this sort of retaining work was undertaken on the Kent and East Sussex railway a few years back, but they used Highway Armco barrier instead of sleepers.

    Good work though.

    ReplyDelete
  3. The tie-bars are a excellent aspect.

    Noel

    ReplyDelete
    Replies
    1. Our P-Way Dept. advised that the tines only extend 150mm below the bottom of the sleepers. We have placed the tie bars 450 below, for extra security. The scheme was prepared by the Engineer along similar lines to what was done on the Severn Valley Railway, some years ago. As we had quite a lot of un-useable concrete sleepers, they were the obvious choice and are very robust and weather resistant.

      Delete
  4. Not a glamorous aspect to railway maintenance but at the same time vitally important to keep on top of so much infrastructure now owned privately. With each line here alone in the UK comes a whole host of civil engineering responsibilities that can't be ignored.
    The SVR has a mighty task ahead of them, too.

    ReplyDelete
  5. What is the problem at Stanway Viaduct that stopped trains running to Broadway from Wednesday this week, please? Terry

    ReplyDelete
  6. Jo, Are you the person to speak to about a pile of used concrete sleepers (Pandrol type fittings like the ones here at the viaduct.

    Powli Wilson
    Powli Wilson

    ReplyDelete
    Replies
    1. I can direct you further. Drop me a line:
      breva2011 (at) hotmail.co.uk

      Delete