Here is a tour of inspection and update of several of them, being bridges 28, 32, 34, 37, 38, and 45. The first 4 are in the Gotherington area, the last on the southernmost tip of the railway.
ACCOMMODATION BRIDGE 37
Work on this bridge was described in an earlier post, and is now complete, with the embankment back filled and re-graded. The two pictures below show you the vast improvement made to this bridge's brickwork:
Before work started, a collapsed wing wall on the up side....
... and a fully repaired wing wall on the down side, a few weeks later.
Here we can see both repaired wing walls on the up side, now in excellent condition. This arched bridge type is less common on the railway; most of our bridges having a metal deck.
There
is still a lot of pointing work remaining to be done, but our budget
this year does not extend to do all that was needed, so just the cracks and
localised areas were done.
ACCOMMODATION BRIDGE 38
Apart
from a final coat of paint on the handrails this bridge is also
completed. The work here was tidying up the pilasters, where vandals had
removed some bricks. In addition the parapet wall on the downside had
to be raised as the ballast was too high and was spilling over onto the
public footpath below. Due to the height of the ballast, the handrail
was too low for safety reasons and so the pilasters were extended
upwards and an extra rail inserted. Some fence repairs were needed, and
Andy Prothero and gang did a brilliant vegetation clearance job, as
shown on his last blog.
Pilaster tops missing, ballast spilling over under the rail.
The same view from underneath, with ballast sitting on the girder
Repair work completed: Extra rows of bricks, higher pilasters with caps, and an extra guard rail.
BRIDGES 28 (STANLEY PONTLARGE, 32 (PRESCOTT ROAD), & 34 (GOTHERINGTON SKEW BRIDGE)
These all had the same problems:-
1. Rotting or missing ballast retaining boards
These
are found on all steel decked bridges and are installed to stop any
pieces of ballast displaced during ballast tamping, or from rail traffic
vibration, from spilling down the sides of the steelwork and falling down onto passing vehicles, or pedestrians. From the sketch
detail attached (see below) you can see that the bulk of the ballast containment is
done by 300 mm high vertical steel plates attached to the deck. Then to
close off the gap back to the web plates of the main bridge girders,
sloping heavy wooden boards (38 mm thick) are fitted. Unfortunately many
of our bridges only have thin (12mm) narrow boards battened together
and these also tend to warp.With the height of the ballast being greater than it
should be, the bottom edges lie in the ballast where they rot away
allowing gaps to form, and, in the worst cases, allowing the boards themselves to
slip down into the gaps!
Here is an example of a missing ballast board, replaced by a plank of wood, but still leaving a large hole.
A worse example is this one on bridge 28, where a piece of ballast board has slipped and is in danger of falling into the road.
Repairs at last! New bigger and thicker ballast boards are being cut to size here, with old examples in the background, and replacements newly fitted in the front.
Here is the drawing of the ballast boards referred to in the first paragraph.
2. End gaps adjacent to the pilasters.
This
is an extension of the ballast board problem, and occurs at the end of
the deck, where there is a gap (varying in width), which again allows
ballast to slip down onto the padstones under the steel girders, and
eventually into the road again. The simple solution was to build a small
brick pier against the pilaster brickwork, to close these gaps.
3. Failure of mortar grout under the padstones (mainly of those beams carrying the track)
The
problem with these is that the mortar breaks down beneath the plates
which supports the ends of the beams that sit on the abutments. The
resulting gap allows the steel beams to move up and down under moving
wheel loads. Without the mortar support the beam ends are then only
supported by the deck plates, and, as we found on the B2B contract, this
leads to plates tearing followed by waterproofing breakdown allowing
water in and causing the steel to corrode. The problem is not an easy
one to solve, as it involves jacking the beam ends and inserting new
grout. A temporary scheme of inserting temporary steel packs has been
carried out, until we have funds to do a better job. Unfortunately there
are no photographs of this work.
One final shot is of an inspection
done on Bridge 45 (Swindon Lane), earlier this year. Quite a tricky one
to get a machine to, but we managed it, thanks to a helpful farmer. The machine is standing on the disused trackbed, in GWSR ownership, south of Cheltenham Race Course station, between Hunting Butts tunnel and Pittville, where our trackbed ownership actually ends.
That
is about all of the bridge work that can currently be done with the budget
available. Hopefully there will be a fresh allocation next year.
Excellent coverage of all the work. I'm sure many of your blog readers are astounded at the hard work and costs involved in catching up on the backlog of maintenance needed on the infrastructure. Does a list of all the 46 bridge
ReplyDeletelocations exist with their chainage details? If so, perhaps it could be put in a future blog.
Thanks for the interest - I hope that the ballast board section wasn't too "educational" !. With the limited budget that we have prioritising the importance of projects is always a problem. I'm just working on the plans for next year now.
ReplyDeleteWe have a complete list of all bridges and culverts on the railway, but it is quite a detailed document, but I will try to provide one just covering the bridges, in the near future.
Many thanks for the prompt reply. Much appreciated.
ReplyDeleteHi, thanks for the informative report. It's good to see the classic structures being so well maintained. I noticed their was a lot of surface rust on the girder span on bridge 38, perhaps a lick of red oxide then black would preserve it? Also the balustrades on bridge 28... Easy for me to comment from my armchair, if I lived nearer I'd get my paintbrush out and get stuck in. Thanks for the blog tho :)
ReplyDeleteHi Mack,
ReplyDeleteIt is something that we think about now and again, as so most of our steel bridges could do with a coat of paint. The difficulty is that the more obvious parts (the lattice parapets and main girder steelwork), that need a cosmetic makeover, as a minimum, are right over live roads and there would be a constant risk of rust, scale or wet paint getting displaced or dropped onto vehicles or people/cyclists passing below, if we attempted it without a partial, or total road closure (cost about £1,300). In addition it would tend to be just a "temporary" job needing re-doing in a few years, unless we went to the vast expense of blast cleaning the whole structure and applying a 3-coat twin pack resin based paint system to give about 25 years life. We just need a lot more money !! Most frustrating!!
There has not been an updated blog for a while so I was wondering whats happening lately with the bridges. Some of the bridges I have seen all look OK from the road but it would good to have a general consensus about the current status of the bridges, just thought I would ask.
ReplyDeleteHi, I was just wondering about the bridge further south of CRC the one that's been causing problems. Are there any pictures of it, or any solutions to its stability problem yet ? The boardroom blog mentioned it and 2 possible solutions. If one is going to cost a yearly expense, and the other considerable repair costs, what are the options? I know they said they had come to a decision not to extend south into Cheltenham, but if you've got to repair the bridge anyway, could not an extension south be possible to an extent? It might bring in more revenue from people nearer the town wanting a trip to the Cotswolds.. Perhaps a feasibility/viability study
ReplyDeleteFor a picture of the bridge in question, you can have a look at my Flickr site of the trackwalk south of CRC:
Deletehttps://www.flickr.com/photos/73536293@N02/albums/72157632569562864
The pictures 12 and 13 refer.