As usual bridge activities since 1
st January 2018 have been mainly about doing visual
inspections of all of our structures, and planning projects for later in the
year. Alastair Watson has done these visual inspections and produced reports
with photographs for over 3 years since the restricted mobility of our structures engineer made it very difficult for him to continue with them.
During January 18, we carried out strike damage repairs to Bridge 1 at Broadway, which were entirely
paid for by insurers Aviva. Damage caused to some of the steel on the Up side
(above the eastbound lane) had required us to impose a 12T weight limit on that
half of the bridge, just when we were trying to lay track into Broadway station! More details of the repairs were included in
Blogs earlier this year.
At the same time as
these repairs, we fitted “LOW BRIDGE” signs on both sides of the bridge as can
be seen here.
Despite these signs, which have large letters
600mm high, the bridge has since suffered another 5 known very minor strikes, the last
being on 1st May 18. These strikes have only caused minor paint
damage and buckled the wasp stripe on the west side, north section. The lorry
owner’s insurers (AXA) have just agreed to pay for the repairs. These will be
done in conjunction with the Collision Protection Beam works (see below).
Another “last
minute” project, which was done in July, is at Bridge 38 near Bishops Cleeve,
which has a Public footpath passing beneath it. This area has, for years, been
a “den” for youths drinking, and causing damage to fencing, bridge brickwork, and
also spraying many lots of graffiti all over the bridge brickwork.
It was
subjected to a very severe graffiti vandalism attack earlier this year. We believe that these youths had also set fire to our Greenmech
vegetation clearing machine a couple of years ago where it was parked under the
next bridge north. It was a total loss.
|
New anti vandal walkway under bridge 38 |
Stones were also recently
thrown at our Drainage gang here, and broken bottles of alcohol were found up on the trackbed. Consequently we have decided to install palisade fencing, to prevent unauthorised track access, to
reduce the area where the youths gathered and to stop them being able to reach
the walls to do any more “artwork”!! Hopefully without a nice sheltered place
in which to congregate they will stop causing us any more trouble.
The fencing work
was done by Gloucester firm Greenfields and was completed in about a week.
The work programme
for the rest of the year is just starting, basic details being as follows:-
1. BRIDGE 1 - INSTALLATION OF A COLLISION PROTECTION
BEAM SYSTEM
The design was
completed by Engineers Halcrow (now part of Jacobs) early this year and tenders
were obtained. Then an order was placed on 25th May with Nu-weld
Engineering Services of Halesowen. Fabrication has been in progress ever since,
followed by hot dip galvanising and then painting to match the bridge steelwork.
|
Channel section during manufacture |
Here is one of the substantial channel sections, seen during manufacture at Halesowen
|
Anchor bolts |
|
A completed channel section |
The system comprises
two heavily welded steel channel section beams which bolt to the upper part of
the abutment brickwork. The beams are in two halves to simplify erection and
fixing. Each beam is fixed to the brickwork with 40 No. 30mm diam resin anchor
bolts, set 650mm into the brickwork.
The actual Collision Protection Beams are
made from 400mm square hollow box sections which are filled with concrete
before installation. These will weigh app. 5.5T each when full of concrete and
are designed to take an impact from a lorry travelling at 45 MPH. They are
positioned app 200mm in front of the bridge steelwork and should deflect no
more than 150mm if such an incident happened. These box beams span the road and
sit on the upstanding brackets you can see on the ends of the abutment beams.
This picture shows the upstanding brackets on the end of the abutment beams. The holes are for the resin anchor bolts which fix them to the abutment behind.
Delivery and
installation started on Monday 3rd September 2018. Each abutment beam
will take about two weeks to install, and a half-road, traffic light controlled
closure will be in place for this work.
The installation of the two
cross beams will take place when the abutment beams are completed and grouting
against the uneven brickwork behind is completed. Yesterday
the two half-beams for the north abutment were unloaded, and temporary Mabey support
columns to take the weight whilst the wall is being drilled were installed.
Here is the north side abutment beam unloaded and ready for installation, to be temporarily held in place by the Mabey support columns.
The completed
installation will look fairly similar to the system installed under the NR main
line in Hyde Lane, Cheltenham:
This bridge has a clearance of 3.9m, less than our bridge at Broadway. As can be seen it has already had plenty of use.
2.
BRIDGE 12 – STANWAY VIADUCT – DETAILED INSPECTION OF
THE ENTIRE STRUCTURE
BRIDGE 8 – B4632 SKEW BRIDGE, STANTON
BRIDGE 7 – STANTON FIELDS PRIVATE ROAD
As part of the
requirement to carry out a Principal Inspection (i.e. a detailed, close up
inspection), of all of our Bridges on a 6-year rolling cycle basis, the time
has come for Stanway viaduct to be done. The work will be carried out by a team from
Bridgeway Consulting Ltd., who are bridge inspection specialists. The structure
has 15 arches, each spanning approximately 12.6m, and rises to approximately 13m high to track level
above the fields below.
The two arches at
each end have sloping embankments under them and one span is over a small
stream. Consequently only 10 arches can be done using a traditional Cherry
picker and the remaining 5 will have to be done using aerial rope workers.
Inspection of the 10 arches will start later this month, as it will not
interfere with train operations. It should take less than a week. However the
rope work requires the main support cables to be attached to the track and so
this work will have to be done in November when no trains are running. Again
about a week’s work will be involved.
It is hoped that Bridges 7 & 8 can
also be done in September, so that the same cherry picker can be used. These
two can be done in a day and we do have an odd train-free day in September to
slot it in.
There are also
problems with ground slippage at each of the 4 end corners of the viaduct.
|
A corner of Stanway viaduct after lineside clearance, and with earlier gabion repair |
|
Failure of temporary wall |
A temporary
solution using redundant concrete sleepers was installed a few years ago, but
as can be seen, these are now leaning over and need to be replaced with a more
substantial long term solution.
|
Concrete sleeper repair |
A similar king – post scheme will be designed
soon but requires some soil sampling to be done first. Our Lineside clearance
team have been doing a great job of clearing vegetation all around this
structure to make the viaduct inspection simpler, and the king-post
design and ground investigation work much clearer.
3. BRIDGE 9 – STANTON AQUEDUCT AND PUBLIC FOOTPATH
This is a 3-span
structure formed from a steel box shaped channel, supported on two trackside
brick piers and two brick or concrete abutments. A public footpath runs along the top of the channel.
|
General view of the aqueduct from below |
The box leaks
and is badly corroded with the steel thickness reduced to approximately half of its original
thickness.
The leaking water here is softening the foundations of the abutment.
This view from above shows the Cotswolds entrance to the channel, and the footpath.
|
Level view of the aqueduct. It was constructed by E. Finch of Chepstow in 1904. |
Bits of scale have been falling off and the wooden walkway is very
unstable, and so it has had to be closed. The entry structure on the Cotswold
side leaks and water is softening the ground beneath the supporting brick
abutment. We have appointed contractor Stepnell and work will start on 1st
November and will take about 6 weeks.
The photographs in the Halesowen factory were taken by John Fancote, a welcome new volunteer recruit for the bridges team. John has spent 41 years working indirectly for Network Rail, mainly as an examining engineer for Amey.
Other photographs and the blog report itself are by John Balderstone, GWSR Structures Engineer.