Gotherington slip repairs - Week 2

The weather has been kind and the progress good. The excavation was completed by the end of the week.



This was despite finding a wet area halfway down the embankment and extra drainage needing to be installed.

So on Friday we were able to undertake a trial of the stone train delivery method. The Racecourse is very kindly letting us use their land at Cheltenham Racecourse to stock pile the stone and the dogfish wagons are loaded there.

In order to empty the wagons RJ Clarke created a bespoke chute which needed some tweaks as the day progressed. We also required the help of the PWay team.


Overall a very successful week. We have approximately 2000 tonnes of material to reinstate and the stone train delivers 80 tonnes a time. It is also not simply a case of dumping the stone in situ. The stone must be compacted in suitable layers.

So the next few weeks will be busy. Additional thanks must be given to those Drivers & Signalman doing extra shifts to enable this repair to go ahead.

Cheers,
Sarah (Infrastructure Manager)