Bridge 1, Broadway
The steelworkers are continuing their formidable task and the principal activities at the moment are:-
(a) fitting bolts to
the two large plates on the Downside, outer main girder:
(c) cutting out corroded parts and installing new steel pieces, brought from the factory, to the outer joggled stiffeners on the downside outer main girder.
The painter has
now left site but has completed the first of two topcoats to the majority of
the deck steel:
A beautiful paint job - and it ain't finished yet! |
A final coat to achieve the necessary thickness will
be applied when all of the steel repairs have been completed. It all looks very
new and shiny and the final coat is yet to come!!
3 The bricklayers
also managed to get a “access slot” in the hectic programme and have installed
the base courses of the ballast retention walls at both ends of the Broadway deck.
They
have also managed to construct a new foundation and the lower plinth section of
the pilaster base on the upside, Cheltenham end. These brick
items will be finished off once all of the steel repairs and final paint treatment
has been completed.
New pilaster base. the old one had been knocked off, and was nowhere to be found. |
Bridge 5, Little Buckland
Excavation of the
north embankment, continues, slowly reducing the ground level behind the
abutment:
Two diggers and two dumpers at work. |
The removal of the old badly fractured and displaced
upside, Broadway end wing wall, has just been completed, leaving a substantial,
extremely tough section at foundation level, adjoining the abutment, the
removal of which would undermine the end of the abutment.
A heavy
machine mounted breaker was used to fetch much of the wall out, but it was
pointless to remove such a tough chunk from a very delicate position.
The level is being checked for depth. Can you see me, Mum? |
Carpenters have
just started work on top of the first section of concrete placed behind the
south abutment. They have been fitting a small timber to the top of the slab
and have inserted dowel bars into the concrete to connect the next section of
concrete to the first. The trough created will be filled with concrete to
form a concrete “kicker” against which the shuttering for the second lift can
be assembled.
The yellow mushrooms that have appeared since our structures engineer was last
on site are of course a safety protection item so that the men do not get
impaled on the dowel bars!!
Bridge 3, Pry Lane
This is a new bridge to our readers. It is a small brick arch bridge in the lane that leads up to the sewage works. It is the least costly of the 5, as it is basically in pretty good condition.
The bricklayers have moved onto that site today to
make a start on the small bits of brick repairs that are needed there. With the launch of work here, only one bridge has not yet been started - bridge 2, on the Childswickham Road. It will be addressed once bridge 1 is completed and released for traffic again, so that this, alternative, bridge can be closed.
Thanks to the very good , dry weather conditions, very satisfactory progress is being made all round.
So if it’s not too much of a presumptuous question, I count one bridge to Honeybourne, is this going to be given the same treatment as the other five, or will we have to wait for the next instalment?! (;-).
ReplyDeleteSo close......