Bridge 5, Little Buckland
After filling in with concrete on Monday, the Cheltenham end abutment
shuttering to the 2nd lift of concrete has been removed and the
space behind has been partly back filled:
At the Broadway end the first
concrete pour behind the wing wall and to the stepped foundation under the
north west wing wall was completed. Setting out for the sloping second
stage shuttering, to form the sloping wing wall concrete backing, was just being
started:
Up side wing wall, first stage of foundations at the back |
Low level of the down side |
The contractor hopes to achieve a further concrete pour on both ends next
Monday (subject to concrete arriving, as promised!). It is very difficult to get materials at the drop of a hat at the moment, there is such a boom in the construction industry.
Bridge 3, Pry Lane
Brickwork pointing to both ends of the Broadway end
abutment wall has been completed, and a few chipped bricks replaced on the
downside end of the arch.
Arch repair |
Pry Lane bridge, in pretty good condition really. Wing wall repair in the background. |
Bridge 1, Broadway
The steelwork repairs are
progressing well, with work alternating between working above deck on dry days
and below deck during wet periods. A lot of heavy hammering could be heard throughout the day today. The badly distorted rail bearer repair is virtually
completed (before & after photos below), as is that to a lesser affected one.
Repaired rail bearer |
What it looked like before the repair |
Perimeter repairs in progress |
With
dry weather today, efforts were being concentrated on fully welding around the
perimeters of the plates tacked into place last week.
Welding the patches, as well as the rain strip to the end of the deck plate |
More updates as soon as we have something to report. It all seems to be going very well, thank you for supporting us !
What's left to pour at the south end, which looks fairly complete? I see some rebar sticking out the top, so given that I assume they are going to pour a tiny bit more on top?
ReplyDeleteAlso, were engineering drawing prepared for this repair, or was it more the contractor looking at the situation and saying 'Oi, that needs a lot of concrete behind it.' Not castigating if so. just curious.
Thanks again for the updates - most interesting!
Noel
Hi Noel,
ReplyDeleteThere is about 1M of concrete to go on the south end, which will bring it up to the underside of the steelwork.
A lot of preliminary detailed inspection work was done and our Engineers - Halcrow carried out design checks and prepared 42 detailed drawings. Then detailed specifications and tender documents were prepared and from these a contractor was appointed. It has been fast and furious ever since as we had to close 2 roads, which always causes issues!!
Thanks for your interest.
John
Thanks very much for the reply!
DeleteI would assume there have also been adjustments to the course as they got into the work (once things are removed/dug out, one always finds things one didn't know about)...
Noel