Bridge 1, Broadway
What a difference a day
makes, sometimes! Major steps forward appear to have been made with several
major items being virtually completed. This actually reflects substantial
progress being made over several days, all drawing to a conclusion in the last
day or so. Lots of welding was continuing today – mainly with patching
corroded sections of the many stiffeners to these large girders. Hopefully
Friday will reveal a big step forwards with completion of many of these too.
Both the two outer main
girders have now been fitted with their new flange plates and almost all of the
high strength tension control bolts having been fitted. Photos below include views of
the bottom flange plates of both outer main girders, a large splice plate with
bolts through 4 plate thicknesses and an action shot of bolt tensioning taking
place.
New Broadway side bottom flange in place, bolts being tightened. |
Evesham side bottom flange now bolted in. |
Large splice plate |
Moth eaten end of main girder. Not good. |
New flange plates fully bolted up. |
There are still quite a lot
of very small items to be done, including the fitting of the new ballustrades.
John, our structures engineer seemed quite upbeat today, having seen the progress on the mechanical works. The end is in sight!
Bridge 5, Little Buckland
The Broadway end abutment has had
the shuttering from Monday's pour stripped, and stone filling between the
concrete and the earth face has been placed and compacted (see below - note the
odd looking, but very effective compacting machine in the foreground).
Compacting ballast at the Broadway end. |
The shuttering has been
installed at the next level for the 3rd pour – see the picture below - and
hopefully that will be done next Monday.
A couple of shots are also
included of the Upside, Broadway end wing wall shuttering, being installed,
which continues to be a really tricky operation. The lowest section of the
completed concrete is now just visible through the safety fencing.
No comments:
Post a Comment