... extra maintenance work has started on bridge 34, the long skew bridge (near our former sleeper depot) over the main road at Gotherington. Here is our report on the work, currently still ongoing.
BRIDGE 34- REPAIR WORKS
During our regular Principal Inspection, some bad corrosion of
the structural steelwork was revealed below the deck on this bridge. During the non-running season window, and with the aid of the PWay department, we have therefore lifted the
track and removed the ballast and old waterproofing materials.
You can see that this is quite a sizeable bridge, double track, and that it crosses the road at an angle.
Removing the ballast has also
revealed rot in the sloping timber ballast boards, and even worse rot in most
of the vertical steel ballast retention plates.
These are now being
cut out and new ones welded in.
This is one of the replacement steel ballast retention plates. You can also see how the deck has been cleared of track and ballast.
More rot
has been revealed in some deck plate edges (see photos), also allowing water
through to the structural steel below.
The plates are many and variable in size
and shape and are being cut on site (see photo). The second photo shows
the cut plates lying roughly in position ready for welding.
This water penetration has caused rotting of parts of
the bottom flanges of the steel beams, in localised areas, where the beam sit
on the padstones on the abutment walls. Notches have formed up to 80mm wide x
300mm long where the steel has been completely eaten away.
Further
rot has been revealed in some of the track bearers and web
stiffeners, all of these will need repairs. To stop the water getting onto the
padstones supporting the steel, deeper end of deck drains are to be installed
(see photo of trench).
Part of the problem is the partial collapse of the ballast retaining walls at the ends of the bridge. These walls stop the ballast falling down on the road, but had failed to do the job properly in recent times. The walls are being broken
out, and will be replaced.
Linked to that, the end of deck drainage
was too high allowing water to get onto the padstones adding to the corrosion
of the steel bearings. (See the deeper drainage trench on the photo further up).
There is also a problem with wear of the padstones beneath where the end bearing plates sit. This is aggravated by the presence of water. (see
photo below of the water filled space).
This allows the ends of the beams to move up and
down under train movements. The movements can cause tearing of the deck plates, so the
track bearer ends will have to be packed and the gaps filled with grout. Once
all of the steel repairs are completed the whole deck will be waterproofed
again.
The largest job of all is to blast-clean and paint the
entire soffit of the bridge. This has not been painted since we acquired the
trackbed about 35 years ago, and probably not in the last years of B.R.
ownership either!!! Blasting and painting requires the entire road space beneath the bridge to
be filled with scaffolding to form a working platform. Being the largest and
longest bridge on the railway the scaffolding is a major task and again a full
road closure has been necessary; no doubt you can see why.
The scaffolding has taken over 10 days to complete.
As you can see we
have provided a walkway through the works to allow pedestrians and cyclists to
get through.
The scaffolding has now been fully sheeted to contain the emissions from
the blasting and painting operations. Blasting started last week and is being
done in phases with priming in between, to stop surface corrosion of the
cleaned steel from starting. We have been told that they may have up to 8
painters on site to get the work done as quickly as possible. Although the work
is mainly underneath the bridge, painting cannot be done if the temperature is
below 5 degrees, so forecasting completion, at this time of year, is almost
impossible. The paint is a 3-coat; twin pack resin based system and should give
at least 20 years before needing any attention.
Whilst the blasting is in progress little other work
can be done in case any of the blast particles find their way through the gaps
between the main girders and the deck plates. Fortunately, as the bridge is so
long that welding can be done at one end whilst paint spraying is done at the
other. The blaster/painters are also planning to work on Saturdays, when no one
else is on site, to minimise any risk of conflict.
The work on bridge 34 is progressing well, but being our largest one everything is taking longer. We have until 27th
February to complete this one, but we have found quite a lot of
corroded steelwork which we did not include originally, but which we
now feel is essential.
Good luck with the repairs to the bridge at Gotherington. It need a lot doing to it, doesn't it ?
ReplyDeleteI hope you are able to get it done within the allotted time. I never realised quite how big this bridge is.
Thanks for the news about the bridge at Broadway. I'm astonished how quickly they've done the repairs I was thrilled to see your PW train once again running over the bridge right through Broadway Station to the northern railhead. Quite a sight ! Sorry. That comment really should be on another blog.
So the Evesham Road is re-opening tomorrow, 26th ?? My fear is that another bridge strike happens before there is permanent protection for the bridge, which I understand might not be until some time in the summer, if it gets the go ahead. So, some anxious time ahead.
Good luck
Peter
Jo, thanks for this report.
ReplyDeleteNice to see the infrastructure being cared for.
It was like going back 20 years or more, when I was doing the same repairs to bridges in the Midlands. Same faults, corrosion to ballast plates, deck plates and angles, rotten ballast boards, poor waterproofing and crumbling ballast walls. Seen dozens of bridges in this and worse condition.
Fortunately, you have the time to do this, we had to do work like this in weekend possessions for deck repairs and waterproofing.
Good idea to lower the drain at the back of the abutment, preventing the water seepage onto the bearings.
Good luck, I hope you get it all done in time.
Hats off to you all. This seems like a very professional operation. It’s good to see the infrastructure getting some funding and much needed attention. Hopefully, when broadway opens, the revenue and visitor numbers will increase and the structures across the whole line will be able to receive more maintainance. Would be good to have a period of consolidation and focus on the whole line.. more welded rail to reduce maintenance, bridge attention and drainage culvert works. Better maintained than network rail! This I feel would serve the railway well for the future, and put it in an excellent position to push north in a few years time :)
ReplyDeleteSouth of hunting butts theirs some railway land too, would be nice dream to see another station their, and perhaps a turntable... need to get lottery ticket.
Mack
Thanks for the report Jo, why isn't this blog on the main index? Very surprised that the bridge has got this bad but the work seems to be well in hand to reopen the bridge and the line very soon, yes, when Broadway opens there should be an increase in revenue and numbers and that should provide more funds for the work like this to be brought up to date! Thanks again for the update.
ReplyDeleteRegards
Paul & Marion
Well it used to be on the main index, and now it's not. I don't know why.
Delete