Here is a little round up of the work in progress, bridge by bridge:
Bridge 2, Childswickham Road
Good progress here, and the steel repairs are due to draw to a close tomorrow. Shot blasting of the
repaired parts and priming of all of the steel will start on Friday.
Corrosion damage to deck ends on bridge 2. Why so bad? See below. |
However the bricklayers have
also been in action thickening out the back of the abutments and piers to
provide support for the ballast retaining walls.
New ballast retaining walls built. |
What appears to have happened
is that, because the abutments both lean inwards by approx. 200 mm, the correct
position for the ballast wall to fit just under the end of the deck plates,
would have been in mid air. The original ones which we removed were set in by
approx. 400mm, leaving the steel exposed to corroding weather effects instead of
being protected. In turn the overhanging deck plates have rotted much more (see top photo) due to that exposure!
Unfortunately the thicker
brickwork that we needed to build from was 1.2m down instead of the 450mm that
it should have been ! The two pictures above show the brick raising
that was required.
Bridge 3, Pry Lane
No news on this bridge for quite a while, but no news is good news in this case. With the completion of the new timber post and rail
fencing up all 4 slopes this bridge is now completed! Another one off the list, two more to go.
Pry Lane bridge from the Cotswolds side - all done. |
Bridge 4, Peasebrook Farm
The first delivery of steelwork and reinforcing has
arrived (see above) and installation will hopefully commence by the end of this
week.
Bridge 5, Little Buckland
News on the Bridges to Broadway EIS scheme:
During the volunteers meeting last Saturday we learned that the EIS share issue had now run its full year, and had closed. The result was - a success ! Final applications were still being processed at the time of the meeting (being the day after the final day) but we have achieved the £500.000 target ! Oh happy day. What wonderful shareholders we have. We own this railway together, and we are forgeing ahead together. The mood during the meeting was ebullient as we learned that the minimum required for the bridges of £500k had been exceeded by approximately 10%. This is brilliant. While we don't know the final costs of all the repairs (due to various problems unearthed along the way), the railway is confident that there will be a bit left over with which to start the extension itself, and the first 800m of new rail have been ordered, and indeed now part delivered as well.
Want to know more? We have set up a new Extension blog for this very purpose. You can follow progress here:
http://broadwayextensionblog.blogspot.co.uk/
There is also a link to it on the side of this blog.
Pat yourself on the back, shareholders. What a great bunch of guys you are.
"What a great bunch of guys you are."
ReplyDeleteI wrote two blogs back that I hope there are gals as well! There are aren't there? Many thanks for an excellent report.
Hi jo, just looking at little buckland bridge, their appears to be an electric line running over the railway bed, is this a first on the railway?... Just wondering if it might be a concern for firemen pulling coal forward on tender and hitting it..
ReplyDeleteYes, but it's quite high up, and certainly not unusual. There are loads of power lines about, and many cross railway lines. The only possible danger is for a crane working under it.
ReplyDeleteThanks for the update. So good to see Little Buckland complete.. Now we have to wait for the track to make it there!
ReplyDeleteNoel