Thursday, 20 November 2014

We've been back to the two bridges being worked on twice over the last two days. There is steady progress!

Here is what we saw:

Bridge 2, Childswickham Road



The gaps beneath all of the steel bearings have been grouted up and the ballast retaining walls are now completed, as shown on the two photographs below.
Looking north, towards Broadway station

Looking south
Note the thicker looking deck plate ends, indicating the drip strip welded on here. This will cause water to run off this side of the ballast retaining wall, also newly installed. No more water running down underneath the girder and causing it to rust!

The lattice parapet steelwork has been made up and delivered. It is expected to go on later this week.

Bridge 4, Peasebrook Farm


Yesterday, the shuttering to the ends of the deck were complete, with the end re-bar cages installed:

 
















When the above two pictures were taken, concreting was due to take place early the following morning (12 to 15 Cu. meters expected).

We then went back today, for a follow up picture:

All is ready for concrete

The rebar cages are all in place, and the shuttering has been erected around it. All is ready for the concrete pour.
Because of the size of the slab it was necessary to transfer the concrete mix in using the excavator bucket, as can be seen on this photograph:






 In this last picture, the concrete is being vibrated in. The Malvern side balustrade is already in place.
 Our next report should show the concrete deck in place, and, we hope, the new balustrades at Childswickham Road.

3 comments:

  1. It appears that surface of the new deck will be somewhat higher than that of the old one? (Not an issue, obviously, just curious.)

    And what's the purpose of the steel pipe running from one side to the other, at the mid-point of the span? Cable duct?

    Great job on the pictures, etc; good to see this phase of the extension on the home stretch!

    Noel

    ReplyDelete
    Replies
    1. The tube is a temporary scaffold pole, which allows a wooden tamper to be drawn across the wet concrete on to the formwork at each side. It makes sure the correct cover of concrete above the reinforcement is maintained. It allows the concrete pour to be levelled in two halves. The pole is removed on completion of the concrete pour.

      Old Builder!

      Delete
    2. "Old builder" is quite correct. The extra feature of it in this case is to create a fall on the surface of the deck from the centre down to a lower level at each end to encourage water to drain away rather than lying on the deck waterproofing. WE have included new drainage at the deck ends to carry the water away down the embankments. Thus the scaffold tube gives the extra height needed to form a fall and also acts as a screeding board for levelling purposes.
      The original drawings that we obtained from Paddington, 30 odd years ago showed app 3" of concrete above the top of the troughing. However when we removed the asphalt waterproofing we found that it was less than 3/4" thick and very poor quality!! The new deck will be roughly the height originally intended plus a bit extra to form the slopes.

      Delete